Mich. Admin. Code R. 460.956

Current through Vol. 24-21, December 1, 2024
Section R. 460.956 - Alternative process

Rule 56. An electric utility may use a process to study interconnection applications that is different from the process described by R 460.954 and R 460.958 to R 460.962. If an electric utility elects to use an alternative process, this process must be described in the electric utility's interconnection procedures.

Mich. Admin. Code R. 460.956

2023 MR 8, Eff. 4/25/2023