Current through Register Vol. 51, No. 21, October 18, 2024
Section 21.10.08.03 - ResponsibilitiesA. A contractor who receives a progress payment or a final payment shall pay a subcontractor an undisputed amount to which the subcontractor is entitled within 10 calendar days of receiving the payment.B. If a contractor withholds payment from a subcontractor within the time period in which the payment normally would be made, the contractor shall: (1) Notify the subcontractor in writing and state the reason why payment is being withheld;(2) Provide a copy of the notice to the prime contractor and, if different, to the person or firm that made the progress payment or final payment to the contractor; and(3) Provide a copy of the notice to the procurement officer.C. Written Notice of Nonpayment.(1) If a subcontractor does not receive a payment within the required time period, the subcontractor shall give written notice of the nonpayment to the procurement officer.(2) The notice shall: (a) Indicate the: (i) Name of the contractor and, if different, of the prime contractor;(ii) Project under which the dispute exists; and(b) Provide an itemized description on which the amount is based; and(c) If known, provide an explanation for any dispute concerning the payment not received.Md. Code Regs. 21.10.08.03
Regulation .03 amended effective July 9, 2001 (28:13 Md. R. 1216)