Md. Code Regs. 20.61.03.03

Current through Register Vol. 52, No. 1, January 10, 2025
Section 20.61.03.03 - Creation of RECs Based on Generation Not Delivered Into the PJM Region

A supplier may request recognition of a REC associated with a Tier 1 renewable source or Tier 2 renewable source not delivered into the PJM region under the following conditions:

A. The electricity is generated at a facility that has been certified by the Commission under COMAR 20.61.02;
B. One of the following:
(1) Certification by the operator of the control area in which the facility is located of the total number of megawatt-hours (MWhs) generated at the facility by month and calendar year; or
(2) If the operator of the control area is unable to make the certification under §B(2)(a) of this regulation:
(a) An affidavit from the operator of the control area attesting that the operator is unable to certify the total number of megawatt-hours generated by the named applicant facility for the specific year in question; and
(b) A certification by the applicant of the total number of megawatt-hours generated at the facility for each calendar year;
C. Certification by the authorized representative of the facility that the RECs associated with the electricity have not expired or been retired, transferred, or redeemed; and
D. The electricity is generated within the PJM Region or in a state adjacent to the PJM control area.

Md. Code Regs. 20.61.03.03

Regulations .03 adopted as an emergency provision effective July 1, 2005 (32:18 Md. R. 1517); adopted permanently effective November 24, 2005 (32:23 Md. R. 1829)
Regulation .03 amended as an emergency provision effective April 1, 2008 (35:9 Md. R. 895); amended permanently effective May 5, 2008 (35:9 Md. R. 899)