SUMMARY: This Chapter establishes administrative and operational requirements for the activities of the Energy and Carbon Savings Trust and its grantees. It includes provisions governing the management of competitive bid processes undertaken by the Trust and of post-grant award evaluation and monitoring of programs and projects funded by the Trust.
C.M.R. 95, 648, ch. 2
This rule was approved as to form and legality by the Attorney General on January 12, 2009. It was filed with the Executive Director of the Legislative Council as a Major Substantive Rule and was provisionally adopted by the Energy and Carbon Savings Trust (94-078 Ch. 2) on December 31, 2008. Following enactment of legislation approving the rule as filed with one amendment at section 3(D), the final amended rule was filed with the Secretary of State on May 29, 2009 (filing 2009-209) for effectiveness on June 28, 2009.
HISTORY NOTES FROM THE SECRETARY OF STATE:
PROPOSAL under 94-078, ENERGY AND CARBON SAVINGS TRUST:
Published November 12, 2008 as 2008-P315 (major substantive)
Deadline for comments: December 15, 2008
PROVISIONAL ADOPTION (MAJOR SUBSTANTIVE):
Filed January 12, 2009 as LR-2009-4
FINAL ADOPTION (MAJOR SUBSTANTIVE):
Accepted for filing May 6, 2009 as 2009-185, to be effective June 5, 2009
Corrected filing accepted May 29, 2009 as 2009-209, effective June 28, 2009
TRANSFERRED by P.L. 2009 Ch. 372 (eff. June 12, 2009) to 95-648, Efficiency Maine Trust
AMENDED:
October 4, 2010 - Section 7 repealed, filing 2010-457
STATUTORY AUTHORITY: 35-A M.R.S.A. §10008 et seq.