65- 407 C.M.R. ch. 334, § 1

Current through 2024-51, December 18, 2024
Section 407-334-1 - APPLICATION OF RULE

No electric utility may enter into any significant agreement or contract, as defined in 35-A M.R.S.A. §3133-A, relating to generating capacity, energy or transmission capacity, unless the Commission has issued a certificate of public convenience and necessity. This Rule also applies to any amendment, extension or renewal of any significant agreement or contract subject to this section for which the original contract was subject to approval by the Commission.

65- 407 C.M.R. ch. 334, § 1