Current through 2024-51, December 18, 2024
Section 407-319-2 - DEFINITIONSA.Commission. "Commission" means the Maine Public Utilities Commission.B.Controlling load forecast. "Controlling load forecast" means the load forecast currently used by the transmission and distribution utilities for transmission and distribution planning purposes.C.Cost-effective. "Cost-effective" with respect to nonwires alternativeshas the same meaning as in Title 35-A, section 3131, subsection 8. D.Nontransmission alternative. "Nontransmission alternative" has the same meaning as in Title 35-A, section 3131, subsection 4-B .E.Nonwires alternative. "Nonwires alternative" has the same meaning as in Title 35-A, section 3131, subsection 4-C .F.Nonwires alternatives coordinator. "Nonwires alternatives coordinator" has the same meaning as in Title 35-A, section 3131, subsection 4-D.G.Small transmission project. "Small transmission project" has the same meaning as in Title 35-A, section 3132-B .65- 407 C.M.R. ch. 319, § 2