The Request for Bids shall permit bidders to provide separate bids for any of the following individual categories, or a single bid for any combination (including all) of the following categories:
Each request for bids shall state the bidding and pricing requirements contained in section 6(C).
At a minimum, the following information shall be provided with each Request for Bids issued pursuant to this Chapter:
Each utility subject to this Chapter shall submit its proposed initial request for bids, including the proposed standard form contract and all other attachments, to the Commission on or before May 1, 1999. For subsequent requests for bids, each utility shall submit its proposed request three months prior to the issuance date of the request for bids. Approval and disapproval of the requests for bids is delegated to the Director of Technical Analysis. The Director shall provide notice to a utility of any questions, objections or grounds for rejection within 30 days after the filing of the proposed request for bids. The Director shall approve or disapprove the request for bids within 60 days after its filing and, if necessary, may order the utility to make specified changes.
Bidders may provide multiple bids. Any individual bid shall be for an individual category, a group of categories specified in the bid, or all categories. Bidders shall provide separate prices for each month of the period for which bids are requested. Bidders shall provide absolute prices and shall not define prices by formulae or by reference to an index.
Bids shall include separate prices for the capacity component in dollars per kilowatt month and the energy component in cents per kilowatt hour. Bids for both components shall include separate prices for peak and off-peak periods as defined in 6(B)(2)(c).
Bids may be in increments of 20%, 40%, 60%, 80% or 100% of the entire category. Any bid for a percentage of the entire category that is greater than 20% shall also include a bid for each 20% multiple up to the highest bid percentage. Bid prices may be different for each 20% increment. Bids shall be for a stated percentage of the capacity and energy available in the entire category, and not for stated amounts of capacity and energy.
65- 407 C.M.R. ch. 307, § 6