17-229-210 Me. Code R. § 5

Current through 2024-51, December 18, 2024
Section 229-210-5 - LOCATION PERMITS
1.Location Permits Required/Not Required

A Utility may not construct new Facilities within the limits of a Highway without applying for and obtaining a Location Permit from the applicable Licensing Authority except as specified herein. [ 35-A MRS§2501, 23 CFR 645 Subpart B]. Private Entities may not apply for or obtain a Location Permit.

A.Location Permit Required

A Location Permit is required in each of the following circumstances:

(1)New Facilities

All new Facilities except as specifically exempted in Section 5(1)(B), Location Permit Not Required;

(2)Certain Facilities Within Compact Areas

Although municipalities are the Licensing Authority for state and state-aid highways within urban Compact Areas and along local roads, the following situations require separate permitting through MaineDOT. MaineDOT will coordinate with Compact Area municipalities in these situations particularly with regard to municipal planning, historic districts and character, including any locally adopted ordinances that establish aesthetic requirements for Monopole, Utility Pole Structure or tower installation:

a) New or relocated Facilities within the limits of a Controlled Access state or state-aid Highway;
b) New or relocated Facilities within the Highway Right-Of-Way installed on, under or within 25' of a state-maintained Bridge. State-maintained bridges may exist on state or state aid Highways or on local roads and can be viewed on the MaineDOT Map Viewer, located on MaineDOT's website;
c) Any proposed Monopole Installation, Utility Pole Structure or tower proposed within the limits of a state or state-aid highway.
(3)Facilities Around Bridges

In addition to the bridges within Compact Areas described above, all new or relocated facilities installed on, under or within 25' of state maintained Bridges outside of Compact Areas. State maintained bridges may be found on the state or state-aid system, or on Town Rights-Of -Way. State maintained bridges may be viewed on the MaineDOT Map Viewer;

(4)Replacement Poles and Underground Facilities

Replacement of the following, regardless of whether those Facilities were previously permitted or deemed legal structures in accordance with 35-A MRS §2309:

a) Replacement of any Utility Pole Structure(s);
b) Replacement of more than 5 Utility Poles located within 5 miles of each other along the same highway corridor within the same year, or
c) Replacement of more than 150 feet of underground Facilities.

For the purposes of this Section, Facilities that exceed these limits are hereby considered new Facilities and not "replacements" or "additions" under 35-A MRS §2503(9).

(5) System Components

Installation of cabinets, transformers or other similar system components that are mounted on pads or multiple poles, not to include standard pedestals or those that are supported on an existing, single pole. Replacement of such Facilities requires permitting only if the existing supporting pad or poles are to be replaced.

(6) Facilities Damaged by Vehicles

Replacement of any aboveground Facility or Appurtenance resulting from damage caused by a vehicle two or more times within the past 12 months.

B.Location Permit Not Required

A Location Permit is not required in the following circumstances, providing the Facility or Appurtenance being installed meets the standards defined herein unless otherwise specified. Where an exception is required, an application shall be submitted in accordance with Section 5(2), Application Process.

(1)Attaching Wires, Cables and Appurtenances

Attaching additional wires, cables or Appurtenances to existing poles, providing the Utility making such attachment has permitted or legally located Facilities under 35-A MRS §2309 upon all of the same poles.

(2)Services

Services, as defined in 35-A MRS §2503(10);

(3)Replacement Utility Poles and Underground Facilities

Replacement of up to 5 Utility Poles within 5 miles of each other along the same highway corridor within the same year, or replacement of up to 150 feet of underground Facilities within the location tolerance as specified in Section 5(4), Installation in Conformance with a Location Permit, with respect to the original location of the Facilities being replaced. Utility Poles replaced under this Section are not required to meet the corridor offsets as specified in Section 11(2)(C), Minimum Corridor Offsets for Utility Poles. Utilities shall not replace Facilities in greater amounts than authorized herein by dividing projects with one primary engineering purpose into multiple, smaller projects.

(4)Existing Conduit

New wires or cables in existing conduit that is either permitted or legally located under 35-A MRS §2309;

(5)Emergency Replacements

Replacement of Facilities that present an immediate hazard or are needed to restore utility service, providing after-the-fact permitting occurs within 60 days when required;

C.Highway Opening Permits

Applicants are advised that, depending upon the type of installation proposed, a separate Highway Opening Permit might also be required from the applicable Licensing Authority.

2.Application Process [35-A MRS Chapter 25]

This Section outlines the application procedures for Location Permits on all Highways and Bridges for which the Maine Department of Transportation is the Licensing Authority. There are two processes available to obtain these Location Permits: Statutory Application Process and the Permit-By-Rule process that was established for certain Utility Pole and attachment installations. MaineDOT reserves the right to require additional information on any applications as necessary.

A.Statutory Application Process [ 35-A MRS §2503]

The Statutory Application Process may be used by all Utilities to apply for a Location Permit.

(1) Submission Requirements

To obtain a Location Permit through the statutory application process, a Utility or authorized agent must first submit a completed application to MaineDOT that includes each of the components listed below. A single application may include multiple Facilities of the same type, provided the general and specific location of each Facility is clearly noted on the application and the Facilities are located along the same road or route, within adjacent towns.

(a)Completed Application Form(s): A blank application form is available on the Utilities Website. Applications shall provide the following information:
(i)Description of the General Location: The description of the General Location shall be as defined in Section 4, Definitions. Alternatively, if the Proposed Installation involves only attachment to existing poles and a permit is required, the description may simply reference the MaineDOT Location Permit number issued to the owner of the poles.
(ii)Description of the Proposed Installation: The description of the Proposed Installation shall be as defined in Section 4, Definitions, and shall include, as appropriate, the type of installation, the size of pipes, the number and kind of poles, voltage and number of phases, and the number of cables, anchors and guys. This Section is not intended to limit future additions as authorized by Section 5(1)(B)(1), Attaching Wires, Cables and Appurtenances.
(iii)Minimum Depth Below / Height Above Ground:The minimum Cover for underground Facilities or the minimum height above the Highway surface for aerial wires and cables.
(iv)Maximum Operating Pressures: The maximum operating pressure must be stated for pressurized pipelines
(v)Statement of Intent to Publish [ 35-A MRS§2503 (2,3,4)]: If a Proposed Installation involves the construction of Electric Supply Lines carrying over 50,000 volts (phase to ground) or the installation of a cabinet, transformer(s) or other similar structure(s) mounted upon a pad or multiple poles, public notice is required. Otherwise, public notice of a Proposed Installation is at the applicant's option. If published, the applicant shall include the text of the application at least one time in a newspaper circulated within the Municipality (or Municipalities) where the Proposed Installation is located. The publication shall include a statement informing any person owning property that abuts the applicable Public Way of their right to file a written objection with the Licensing Authority within 14 days after publication. Evidence of publication shall be submitted to MaineDOT before a permit can be issued. If not published, the application will be processed and objections filed in accordance with 35A MRS §2503(3). Objections received in this manner could result in the applicant being required to relocate the Facility and all Appurtenances at its expense.
(vi)Owner's Signature: The owner or operator of the Proposed Installation must sign the application. Any person signing on behalf of the owner or operator must provide evidence of authorization to sign.
(vii)Construction by Others: If a Proposed Installation is to be constructed by a person or entity other than a Utility, that person or entity shall include a signed letter with the application acknowledging complete responsibility for the Proposed Installation until such time as the Facility is conveyed to a Utility. In no case shall a Proposed Installation constructed by others be connected to a Utility system or network prior to such conveyance unless otherwise permitted.

Applications submitted in this manner shall be signed by the Utility to indicate its agreement with the location of the proposed Facility and its intent to accept the Facility upon completion of construction. If a Location Permit is issued, it will include a special condition acknowledging construction by a non-Utility.

(b)Specific Location Plan(s): The Specific Location Plan must conform to the definition in Section 4, Definitions. A separate Specific Location Plan shall be submitted for each proposed Facility. Specific Location Plans shall be submitted on standard letter, legal size or 11-inch by 17-inch sheets (for archive purposes) with no more than two Highways being shown on one sheet.

If the Proposed Installation involves wire attachment to existing poles and a permit is required, the plan may simply locate the starting and ending points in relation to any of the major features indicated in the General Location. Offsets to existing poles are not necessary in this situation.

Similarly, If the Proposed Installation involves sporadic attachments to existing poles that are located along a single corridor, within adjacent towns, the plan may simply locate the starting and ending points and include a list of the poles and corresponding coordinates that are associated with the application. Offsets to the existing poles are not necessary.

(c)General Location Map: For each Proposed Installation, the Utility must submit an accurate area map. Examples include MaineDOT Map Viewer plan available on the MaineDOT website, MaineDOT Highway plan or U.S.G.S. quadrangle.
(d)Supporting Data: All applications must also contain statements that clearly indicate the following:
(i) Whether joint use or ownership of the Facility is anticipated within a year of the date of initial installation.

If the Proposed Installation involves attachment to the poles of another Utility, a copy of the lease or agreement showing evidence of the right to occupy the poles shall be included with the application. Alternatively, the application may also be signed by the Utility that owns the poles.

(ii) Whether there are any existing Facilities of others located within the minimum clearance offset specified in Section 9(1)(I), Clearance Between Facilities;
(iii) That a copy of the application has been submitted to the municipal clerk of each Municipality or the clerk of the County Commissioners in the case of unorganized townships where the Facility is located; and
(iv) The name, address and telephone number of a person who will be available to answer questions regarding the application and to review the Proposed Installation on-site.
(e)Special Materials: If any part of the Proposed Installation is to be made within an area constructed with Special Materials the application must include plans showing the location, method of construction, clearances and other data pertinent to how the Proposed Installation may impact those areas.
(f)Attachment to MaineDOT Highway Structures:If any part of the proposed installation of Facility is within 25 feet of a Bridge or proposed to be attached to a Bridge or other Highway Structure, the application must include plans showing the location, method of construction, clearances and other data pertinent to the Proposed Installation. Please refer to Section 11(1)(C), Use of Existing Department Poles or Structures for additional information regarding attachments to MaineDOT Poles or Structures.
(g)Traffic Control Plan: Any work proposed within the limits of a Freeway shall include a Traffic Control Plan as defined in Section 4, Definitions. Specific requirements are further described within Section 7(7)(B), Freeways.
(2)Processing

The application shall be submitted to MaineDOT at the address provided on the application form. A complete copy shall also be submitted to the municipal clerk of the Municipality or the clerk of the county commissioners in the case of unorganized townships where the Facility is located. The application will be reviewed with primary consideration given to the standards defined within this rule; however, specific site conditions, proposed work in the same General Location, public comments, or other concerns of MaineDOT will also be considered. Permits will normally be processed within 30 Days; however, up to 60 Days is permissible. [ 35-A MRS§2503(19) ]

(3)Completion Confirmation

Upon completion of its review of the application, MaineDOT will send the Utility a Completion Confirmation Form along with an approved Location Permit with conditions if applicable. Upon completion of the installation of a permitted Facility, the Utility shall return the completed form to MaineDOT, stating that all work has been completed in accordance with the specified permit. If field modifications were necessary or the scope of the original project was reduced, amended sketch plans from the original permit shall be submitted to indicate the changes. If field changes beyond the tolerance specified in Section 5(4), Installation in Conformance with a Location Permit, were necessary, the name of the MaineDOT representative and the date of all applicable approvals shall be indicated on the form. All amendments submitted as described above shall be deemed accepted by the MaineDOT unless MaineDOT notifies the Utility otherwise within 60 days of receipt.

B.Facility Locations or Relocations Authorized Through MaineDOT Projects

Locations or relocations of Facilities authorized through MaineDOT Projects are permitted through the coordination process that occurs in the Preliminary Engineering phase of a MaineDOT Project. Through this process, the Utility Coordinator and a representative from the Utility work together to determine the best location for the proposed or relocated Facilities. The Utility then designs its Facilities and Appurtenances in accordance with the accommodation standards defined within these rules or as otherwise authorized by MaineDOT. Once all available information regarding the new location of the Facilities is submitted to and accepted by MaineDOT, a Location Permit for the relocated facilities will be issued to reflect the change and to evidence the legality of the new location. This paragraph shall only apply to Facilities that must be relocated because of the MaineDOT Project. New Facilities (not replacement Facilities) must be permitted as otherwise described herein. [ 35-A MRS§2503(8) ]

C.Permit-By-Rule (PBR)
(1)Applicability

The Permit-By-Rule process is not available within Freeways, Controlled Access corridors or Scenic Byways.

Pursuant to 35-A MRS §2503(8), the PBR rules do not apply to the following:

a) relocation of facilities when the relocation is required because of the construction, reconstruction or relocation of the roadway;
b) Utility Pole Structures or any other type of pole requiring reinforcing foundations along or adjacent to the pole base regardless of foundation material type;
c) any pole line carrying over 50 kV;
d) any poles or wires that do not meet all of the requirements defined in Section 11, Aboveground Installations (e.g. substandard spacing/clearances, replacement poles proposed to be closer to the road, poles not meeting minimum offsets, etc.);
e) poles that exist at greater offsets in accordance with Section 11(2)(C), Minimum Corridor Offsets for Utility Poles;
f) or any officially designated historic districts or areas regardless of Compact Area status.

When utilizing the Permit-By-Rule process, Utilities remain subject to all of the responsibilities and liabilities set forth in 35-A M.R.S.§2503 as specified herein.

(2)Utility Options, Responsibilities and Liability
(a)Authorization: In cases where a Utility is required to obtain a written location permit to install Utility Poles, wires, wireless facility attachments and/or other authorized attachments as defined herein, a Utility, at its option, may utilize the Permit-By-Rule process rather than the Statutory Application. Facilities properly installed pursuant to these rules are legal structures within the meaning of 35-A M.R.S. §2503(16).
(b)Utility Responsibilities / Liability:To qualify for the PBR process, the Utility must submit sufficient documentation to demonstrate compliance with this rule. If sufficient documentation is not submitted in the form and manner required by this rule, then the automatic approval procedure set forth in Section 5(2)(C)(5), PBR Processing, will not apply.

The Utility shall be fully responsible for the design, construction, maintenance and operation of its facilities and, to the extent provided by 35-A M.R.S. §2503(6), for any damages resulting from the Utility's negligence in the installation or maintenance of said facilities and its appurtenances.

The Utility shall be fully responsible for moving or removing a facility installed in violation of this rule and all associated costs.

(3)MaineDOT Options and Responsibilities
(a)Imposition of Stricter Design Standards :Before the date of automatic approval as set forth in Section 5(2)(C)(5), PBR Processing, the Department may require that such a Facility meet additional and/or more stringent design standards than those contained in this rule, including greater pole offsets, when the Department determines that such standards are in the best interests of public safety.
(4)General Application Submission Requirements

To receive a permit using the PBR process, a Utility must submit the PBR application package to the applicable MaineDOT Region Office. The application package shall conform to the requirements of Section 5(2)(A)(1), Submission Requirements, and shall indicate that the PBR process is to be used.

(5)PBR Processing

PBR applications are automatically approved within the time frames indicated below and in accordance with this rule.

(a)Projects Involving 10 or Fewer Utility Poles, Wires, and/or Wireless Facility Attachments: If the Utility is not notified of any objections by MaineDOT within fourteen (14) days from the date of receipt of a properly filed PBR application, then the application is automatically deemed approved and the permit is automatically issued without any further notification from MaineDOT for projects involving 10 or fewer Utility Poles.
(b)Projects Involving More Than 10 Utility Poles, Wires, and/or Wireless Facility Attachments:If the Utility is not notified of any objections by MaineDOT within thirty (30) days from the date of receipt of a properly filed PBR application, then the proposed facility location is automatically deemed approved and the permit is automatically issued without any further notification from the Department for projects involving more than 10 Utility Poles.
(c)Division of Projects Prohibited: Utilities shall not divide projects having one primary engineering purpose and more than 10 Utility Poles into multiple projects involving 10 or fewer Utility Poles.
D.Additional Process for Significant Facility Installations
(1) Evidence of Coordination with Adjacent Utilities

In addition to the applicable application process described in Sections 5(2)(A), Statutory Application Process, and 5(2)(C), Permit By Rule,Proposed Installations involving underground Facilities of at least 500 feet in length (excluding new or replacement wires or cables within existing Encasement) or the installation of 25 or more Utility Poles require evidence of coordination with at least one representative from every Utility having existing or Proposed Installations within the General Location. Coordination may occur individually with each Utility or through Coordination Meeting(s). Notice of Coordination Meetings will be provided by the entity proposing a new project at least one week in advance of the actual meeting date. A reasonable effort shall be made to assure the availability of as many attendees as possible. Additional evidence submitted with the Location Permit application shall include:

(a) Identification of all known Utilities having existing or Proposed Installations in the General Location,
(b) The name and telephone number of each individual associated with each of the Utilities identified in subparagraph (a) above,
(c) Identification of any major concerns expressed by the other Utilities and how each concern will be addressed.

The form which should be used to confirm this coordination is located on MaineDOT's Utility website as part of the Location Permit application.

(2)Copy of Permit Application to Connect ME Authority

When a Utility proposes any underground installation of at least 500 feet in length, a copy of the permit application shall be submitted to Connect ME Authority by the Utility in accordance with 35-A MRS §2503, sub § 2. When such work is associated with a MaineDOT project, this notification is not required by the utility as notice of the project has already been provided through MaineDOT's Work Plan.

E.Field Layout for Utility Poles and Utility Pole Structures

Each pole being permitted shall be staked in the field and numbered in such a manner that the numbering is visible from the shoulder of the road. The pole numbers presented on the permit application sketch shall match the pole numbering used in the field.

3. Lapse of Permit

Permits granted pursuant to these rules shall expire if substantial construction of the Proposed Installation is not commenced within 12 months of the permit date or if construction work is suspended for one or more entire Construction Seasons.

4.Installation in Conformance with a Location Permit

As determined by MaineDOT through its application review process, specific permits may include requirements beyond the minimum standards stated within these rules to the extent necessary to protect the traveling public, minimize conflicts or ensure the efficient use of the Highway corridor. Proposed Installations or replacements shall be installed as permitted. If changes beyond the offset tolerance of the permit become necessary, the Utility shall notify MaineDOT to request permission to amend the application or, if a permit has already been issued, request that MaineDOT amend the permit.

Unless otherwise specified in the permit, field changes are considered to be within the horizontal offset tolerance of the permit provided they comply with allof the following:

A. The offset of the modified location of aboveground Facilities is within 10 feet of the permitted location and no closer to the Highway, or the offset of the modified location of underground Facilities is within 18 inches of the permitted location;
B. The modified location does not conflict with any existing Facilities, Appurtenances, Highway features (i.e. sidewalks, drainage pipes, Curb, entrances, etc.), or other Proposed Installations within the Highway; and C. The modified location otherwise complies with all standards defined in these rules.
5.Unauthorized or Non-Compliant Facilities

Any Facility installed within the Highway limits that are not in compliance with the terms of its Location Permit, 35-A MRS Chapter 23, 35-A MRS Chapter 25, or these rules, will be considered an Unauthorized or Non-Compliant Facility. As such, that Facility cannot legally remain within the Highway limits unless the location is otherwise authorized by deed or easement. Within 5 days' notice from MaineDOT, the entity owning or operating the Unauthorized or Non-Compliant Facility must correct any violations of the Location Permit or applicable rules herein. If the Utility fails to correct the violations of its Location Permit, MaineDOT may revoke the existing Location Permit and require removal of the Facility and all Appurtenances.

6.Private Facilities

Since private Facilities located within the Highway limits reduce the available Right-of-Way for public use, there are greater restrictions placed upon them. Upon receipt of a complete application from a Private Entity and with consideration of the standards provided herein, MaineDOT may, but is not required to, issue a Private Facility Exception License to permit a private Facility to exist within the limits of the Highway. Said permit shall be valid only if it does not interfere with the Highway, its maintenance or any of its uses.

If MaineDOT determines in its sole discretion that the private Facility interferes with Highway use and/or maintenance, it can order the private owner to remove the Facility in a manner acceptable to MaineDOT. The Facility owner shall bear all costs relating to the Facility and any Appurtenances including installation, relocation, adjustment and removal. Owning a private Facility within the Highway limits does not guarantee continued use.

Note that Municipalities construct, own and are responsible for the maintenance of their facilities, for example, conduit systems for ornamental lighting or elimination of aerial electric lines. Municipal facilities such as conduit systems for lighting shall not be considered "Private Facilities" for the purposes of this section. All other requirements for facilities in State and State-Aid Rights-Of-Way shall apply as appropriate.

A.Application

Applications for Private Facility Exception Licenses may be obtained from the Utilities Website and shall include any applicable information as specified in Section 5(2)(A)(1), Submission Requirements. First-time applicants are encouraged to contact MaineDOT to review the application requirements. In instances where a private Facility or Appurtenance is proposed in a Highway in front of property not owned by the applicant, a letter from that abutting property owner stating no objection to the proposed installation shall accompany the application. (Note: A Facility is deemed "in front of" a parcel of property whenever it is located between the centerline of the Traveled Way and the Right of Way line adjacent to the subject parcel).

B.Crossings

Private Facilities, not directly connected to a Utility distribution system or network or having characteristics that are not detrimental to the highway, will normally be authorized to cross Highways, providing all applicable standards are met as well as any special requirements specified by MaineDOT.

C.Longitudinal Installations

Private installations parallel to and within the limits of the Highway will not normally be authorized. However, where a proposed installation is less than 500 feet in length, MaineDOT will consider each application on a case-by-case basis.

17-229 C.M.R. ch. 210, § 5