Applications, Construction Plans, Technical Specifications, Permits and Fees of Aboveground Flammable Liquid Storage Facilities. (Note: see Title 25 M.R.S.A §2481 through § 2484 ).

1. The construction plans and technical specifications for storage facilities exceeding 1,320 gallons, in one or multiple tanks, shall be certified by a professional engineer.
2. A permit is non-transferable pursuant to Title 25 M.R.S.A §2481,(5). A person acquiring an existing facility must notify the Office of the State Fire Marshal within 180 days of assuming ownership of that facility.