Subsection 214-3-3.54 - PLANS AND SPECIFICATIONS

The plans and specifications for a new or reconstructed impounding structure shall consist of the following as a minimum:

a. The name of the project; the name of the owner; classification of the impounding structure as set forth in Chapter 3 of these regulations; designated access to the project; and the location with respect to highways, roads, streams, and existing impounding structures and impoundments that would affect or be affected by the proposed impounding structure.
b. Cross sections, profiles, logs of test borings, laboratory and in situ test data, drawings of principal and emergency spillways, and other additional drawings in sufficient detail to indicate clearly the extent and complexity of the work to be performed.
c. The technical provisions, as may be required to describe the methods of construction and construction quality control for the project.
d. Special provisions, as may be required to describe technical provisions needed to insure that the impounding structure is installed according to the approved plans and specifications.

Plans and specifications shall be submitted with the final design report.

e. The owner shall notify the Agency of any proposed changes in design, plans, and specifications that will affect the safety of the impounding structure.