Current through 2024-51, December 18, 2024
Section 096-592-10 - Inspection of treatment systemAll construction under program grants pursuant to this chapter must be inspected as follows:
A.Engineered subsurface or overboard discharge systems.For subsurface disposal systems with wastewater flow greater than 2,000 gpd, or overboard discharge systems, the services of an on-site inspector hired by the consulting engineer are required.B.Non-engineered subsurface systems. For subsurface disposal systems with wastewater flow less than 2,000 gpd, inspection by the local plumbing inspector or code enforcement officer is required. Additional inspection by a site evaluator, consultant, or department project representative may be required by the contract documents.06- 096 C.M.R. ch. 592, § 10