Current through 2024-51, December 18, 2024
Section 096-403-7 - Facility Closing and Closing PlanApproval is required to close an incineration facility. The owner or operator of the incineration facility must submit the information required below to the Department in a time frame and manner that will allow the owner or operator to meet the financial assurance requirements of 06-096 CMR 400, section 11 of these rules. At a minimum, this information must include:
A. An anticipated date for facility closure and for removal of all wastes; B. A description of any anticipated or known contamination on the facility site and how that contamination would be monitored and/or treated;C. The proposed use or disposition of the facility site and all of the structures and equipment from the facility; D. The proposed closure and post-closure care actions that will be taken and their anticipated costs; andE. Financial assurance complying with the requirements of 06-096 CMR 400(11) of these rules.06- 096 C.M.R. ch. 403, § 7