Section III-2107 - Program RequirementsA. General Requirements. In order for the department to be able to adequately assess the merits of the proposed project, applications must be complete and verifiable. The responsibility to provide complete, accurate, and documented data on each project, as defined herein, rests solely with the port authority submitting the applications for funding.B. Specific Requirements 1. Project and Total Projecta. For purposes of this program, a project is that activity that derives benefits to the state after an investment of program and port funds. "Project" refers to that portion of the total project for which the port is seeking program funds from the department. The amount of program funds required is used in calculating the cost benefit ratio which is used for ranking projects.b. The "total project" is that activity that derives benefits to the state after an investment of program, port and other public and private funds and its cost is used to determine if the requirement for a minimum cost benefit ratio of one is met except as provided herein in references to benefit-cost ratio for projects with a private investment equal to or greater than the program share. The "total project" includes all improvements that are necessary for both the public and private sectors in order to derive the benefits identified in the application.2. Local Match a. Each port authority shall provide a local match of at least 10 percent of the cost of constructing the project. Funds obtained from federal or other non-state sources (i.e., private donations) may be used for the local match. State funds cannot be used as local matching funds. Prior to advertisement for bids, verifiable evidence shall be submitted indicating that all non-program funds are in hand or are readily available.b. A port authority may provide a local match greater than 10 percent. Since the state's investment is the cost in calculating the benefit-cost ratio, the cost/benefit will be greater if the port elects to provide a larger local match. A higher cost/benefit will result in a higher evaluation score.3. Land Acquisition a. Land acquisition shall be eligible for funding only when in the judgment of the department it is an integral component of a project and critical to its development. Land acquisition that is not a critical component of a project or that is intended to be used for future expansion of port facilities is not eligible for funding. An application must be developed which presents costs, benefits and other date for the total project.4. Port-Owned or Public Landa. Port improvements funded through the Port Construction and Development Priority Program shall be built, installed, and/or implemented only on port-owned lands or public lands. Public lands are lands owned by public organizations which are authorized by law to perform governmental functions.b. Prior to advertisement for bids, port authorities shall submit verifiable evidence that they either own the land or they have entered into an agreement with the public body that owns the land.5. Number of Applications. An application shall be prepared for each project. If a port authority submits more than one application in a given quarter, the port authority shall prioritize them for review purposes. The top priority project shall be labeled "Priority One" on the title sheet of the application. The next priority project shall be labeled "Priority Two", etc. Due to time constraints and available personnel to evaluate the applications, the department may restrict the evaluation to only the top two priority projects per port in a given application year.6. Types of Projects. The types of projects that shall be funded by the program shall be limited to the construction, improvement, capital facility rehabilitation, and expansion of publicly-owned port facilities including intermodal facilities and maritime-related industrial park infrastructure development, such as wharves, cargo handling capital equipment, utilities, railroads, primary access road, and buildings which can be shown to be integral components of any port project submitted for funding.7. Navigation Projects. Funding from the program will not be integrated with or used for the state sponsorship (state matching basis for federal appropriation) for new construction and/or maintenance dredging on federally authorized navigable waterways.8. Project Commencement. At the application state, projects must be developed sufficiently to allow them to commence within the fiscal year that they are funded. Execution of the project agreement with the department and receipt of preliminary plans by the department shall constitute commencement. Preliminary plans at this stage must be more advanced than plans submitted with the application. Projects that do not commence within the fiscal year that they are funded will result in forfeiture of program funds.9. Forfeiture of Program Fundsa. If a port authority does not execute the project agreement furnished by the department and return it to the department within 90 days of being mailed to the port authority, then the state funds authorized from the Port Construction and Development Priority Program may be forfeited.b. If a project is not commenced within the fiscal year that it is funded, then the state funds authorized by the program may be forfeited. A project is considered to have commenced upon delivering the executed project agreement and the preliminary plans to the department. Preliminary plans submitted with the application shall not meet this requirement.c. If a project is canceled due to not beginning construction within the time frames provided for under the Section on distribution of funds, program funds may be forfeited. Projects which are canceled and program funds forfeited in this manner shall be treated in accordance with the provisions of R.S. 34:3456(A).d. Advertising a project for bids to construct the project prior to obtaining written notice from the department may result in forfeiture of program funds.10. Selling Lands, Facilities, or Equipment. Should a port authority sell or dispose of any facilities or equipment, that have been funded in part by the Port Construction and Development Priority Program, the port authority shall reimburse the department for the percentage of project life remaining at the time of the sale. The project life shall be 20 years for structures and 10 years for equipment unless a different period of time is specified in the evaluation of the project. If the land obtained through the program funds is sold at any time DOTD shall be reimbursed at one hundred percent of the original funds dispersed for the purchase of the land including change orders unless the land is transferred to another Public Port subject to the Port Construction and Development Priority Program Rules and Regulations.11. Maintenance. The port authority is responsible for maintenance and will structure its revenue rates to adequately fund maintenance costs. The port authority may execute an agreement with a tenant providing for maintenance of the project to be funded by the tenant. If such an agreement is executed, then the expenses used for the evaluation of the project will be reduced as explained herein in the Section entitled "Minimum Return on the State's Investment."12. Discount Rate. The discount rate used in the evaluation process shall be based on the interest rate paid on 20-year U.S. Treasury Inflation Protected Securities (TIPS) which is currently 2.375. The rate will be evaluated every two years and may be adjusted by agreement between the department and the Ports Association of Louisiana (PAL). The adjusted rate will be available from the department upon request.13. Minimum Return on State's Investment. The minimum rate of return for the state's investment shall be the discount rate as stated herein. This evaluation shall be based on no growth. In calculating the rate of return for this criteria, the cost shall be the total program funds invested. The benefits for this calculation shall be the port revenues less expenses associated with the proposed project. Expenses shall include maintenance and expected operational costs. Generally, the minimum allowance for expenses will be no less than the project cost divided by the project life. If the port authority executes a conditional lease with the tenant and the tenant provides all maintenance, then the minimum expense may be one-half of the project cost divided by the project life. Also, see "Private Investment." The evaluation period shall be the life of the project. If the port sells bonds in order to finance all or a portion of the private investment, only revenues in excess of debt service, operating expenses and satisfaction of bond buyer reserve accounts may be used to determine the return on the state's investment. The minimum rate of return is calculated without growth and without additional inflation. The port should establish its fees based upon inflation and market conditions.14. Benefit-Cost Ratio. Only projects that have a benefit-cost ratio equal to one or more shall be funded by the Port Construction and Development Priority Program. In calculating the B/C for this criteria, the cost is the total investment, both public and private, required to implement the total project and derive the benefits. For projects that have a private investment that is equal to or greater than the amount of program funds required, the project may be exempted from this requirement. If exempted the project must meet a program benefit-cost ratio equal to one or more. The cost for the program benefit-cost ratio is equal to the amount of program funds required for the project.15. Monitoring a. For five years after completion of a project funded by the Port Construction and Development Priority Program, the port authority shall submit to the department a report comparing the actual benefits derived with the estimated benefits associated with the project. This report shall be submitted in accordance with the current edition of the Louisiana Port Construction and Development Priority Program Procedures Manual for Funded Projects. The source of data for the actual benefits shall include audited financial statements and other statements from the port authority. Significant deviations will be noted and proposed corrective actions, if needed, will be indicated. The report shall be certified true and correct by the executive director of the port authority.b. Port authorities that do not comply with this provision will be ineligible to participate in the program until they are determined to be in compliance by the department. The department may audit the reports at program expense.16. Private Investment. If the private investment exceeds the program investment, then the deduction for expenses may be reduced by the factor derived by dividing the program investment by the private investment. Also, refer to Paragraph 14 "Benefit-Cost Ratio" for possible exemptions to the benefit-cost ratio required for funding.17. Conditional Projects a. Projects that meet all of the following conditions may be considered conditional projects: i. the project must have a total project cost of at least $15 million;ii. the private investment must meet or exceed the program share;iii. the participation of the private sector is contingent upon the availability of program funds, andiv. the application must demonstrate that all parties worked diligently to submit a complete proposal, but due to factors beyond their control, private sector/local share of funding is not assured.b. A project that meets the above criteria may be evaluated as having immediate need if all other program requirements are met except the availability of the local and/or private share. If it meets all other requirements and is incorporated into the priority list recommended to the legislature, it will be designated as a conditional project. The sponsor will have 18 months from the date of the letter from the department notifying them of the project's funding to submit documentation that arrangements for the private sector and local share have been finalized. If after 18 months the documentation has not been submitted to and approved by the department, project funding will be withdrawn. If the sponsor desires to seek funding for the project, it will have to submit a new application and compete as a new project. The department may limit funding for these projects to a token amount based on availability of funding.La. Admin. Code tit. 56, § III-2107
Promulgated by the Department of Transportation and Development, Division of Flood Control and Water Management, LR 18:751 (July 1992), repromulgated by the Department of Transportation and Development, Office of Public Works, LR 31:942 (April 2005), amended LR 34:1042 (June 2008), Amended by the Department of Transportation and Development, Office of Multimodal Commerce, LR 491436 (8/1/2023).AUTHORITY NOTE: Promulgated in accordance with R.S. 34:3451-3463.