Section XV-5347 - Hydrologic Balance: Post-Mining Rehabilitation of Sedimentation Ponds, Diversions, Impoundments and Treatment Facilities
A. Before abandoning a permit area or seeking bond release, the operator shall ensure that all temporary structures are removed and reclaimed, and that all permanent sedimentation ponds, diversions, impoundments and treatment facilities meet the requirements of this Chapter for permanent structures and impoundments. The operator shall renovate such structures if necessary to meet the requirements of this Chapter and to conform to the approved reclamation plan.

La. Admin. Code tit. 43, § XV-5347

Promulgated by the Department of Natural Resources, Office of Conservation, LR 5:395 (December 1979), amended LR 14:441 (July 1988), LR 20:447 (April 1994).