Current through Register Vol. 50, No. 11, November 20, 2024
Section XV-2103 - General Requirements: Coal Development OperationsA. Any operator proposing to undertake development operations which involve the removal of substantial quantities of overburden with explosives or power earthmoving equipment to determine quality, boiler design criteria, the feasibility of removing lignite or coal and other testing purposes shall submit an application for a development operations permit to the commissioner prior to commencing any such operations. A permit fee of $75 shall accompany each application.La. Admin. Code tit. 43, § XV-2103
Promulgated by the Department of Natural Resources, Office of Conservation, LR 5:395 (December 1979), amended LR 6:177 (May 1980), LR 14:441 (July 1988), LR 20:447 (April 1994).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:901-932.