La. Admin. Code tit. 43 § XIX-3937

Current through Register Vol. 50, No. 11, November 20, 2024
Section XIX-3937 - Time of Commencement
A. Unless circumstances indicate that undue hardship would otherwise result, every applicant shall commence proceedings under these rules of procedure so as to permit the application to be docketed, advertised, heard and properly considered for at least 15 days before the order is issued.

La. Admin. Code tit. 43, § XIX-3937

Adopted by the Department of Natural Resources, Office of Conservation, October 1983, amended and promulgated by the Department of Natural Resources, Office of Conservation, LR 19:764 (June 1993).

AUTHORITY NOTE: Promulgated in accordance with R.S. 30:4 et seq.

NOTE: If at all possible, any application hereunder should be received in the Baton Rouge office of the Office of Conservation at least 45 days before the application is to be fixed for hearing.