Current through Register Vol. 50, No. 11, November 20, 2024
Section XIII-3309 - How Can an Operator Change Its Integrity Management Program? [49 CFR 192.909]A. General. An operator must document any change to its program and the reasons for the change before implementing the change. [ 49 CFR 192.909(a)]B. Notification. An operator must notify OPS, in accordance with §518, of any change to the program that may substantially affect the programs implementation or may significantly modify the program or schedule for carrying out the program elements. An operator must provide notification within 30 days after adopting this type of change into its program. [49 CFR 192.909(b)]La. Admin. Code tit. 43, § XIII-3309
Promulgated by the Department of Natural Resources, Office of Conservation, Pipeline Division, LR 30:1274 (June 2004), amended LR 31:686 (March 2005), Amended LR 461598 (11/1/2020).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.