Section XIII-1725 - Underground Clearance [49 CFR 192.325]
A. Each transmission line must be installed with at least 12 inches (305 millimeters) of clearance from any other underground structure not associated with the transmission line. If this clearance cannot be attained, the transmission line must be protected from damage that might result from the proximity of the other structure. [49 CFR 192.325(a)]
B. Each main must be installed with enough clearance from any other underground structure to allow proper maintenance and to protect against damage that might result from proximity to other structures. [49 CFR 192.325(b)]
C. In addition to meeting the requirements of Subsections A or B of this Section, each plastic transmission line or main must be installed with sufficient clearance, or must be insulated, from any source of heat so as to prevent the heat from impairing the serviceability of the pipe. [49 CFR 192.325(c)]
D. Each pipe-type or bottle type holder must be installed with a minimum clearance from any other holder as prescribed in §1135.B [49 CFR 192.325(d)]

La. Admin. Code tit. 43, § XIII-1725

Promulgated by the Department of Natural Resources, Office of Conservation, LR 9:233 (April 1983), amended LR 10:525 (July 1984), LR 20:446 (April 1994), LR 27:1542 (September 2001), LR 30:1247 (June 2004), Promulgated by the Department of Natural Resources, Office of Conservation, LR 461586 (11/1/2020), Amended LR 471144 (8/1/2021).