Current through Register Vol. 50, No. 11, November 20, 2024
Section XIII-1321 - Inspection and Test of Welds [49 CFR 192.241]A. Visual inspection of welding must be conducted by an individual qualified by appropriate training and experience to ensure that [ 49 CFR 192.241(a)]: 1. the welding is performed in accordance with the welding procedure; and [ 49 CFR 192.241(a)(1)]2. the weld is acceptable under Subsection C of this Section. [ 49 CFR 192.241(a)(2)]B. The welds on a pipeline to be operated at a pressure that produces a hoop stress of 20 percent or more of SMYS must be nondestructively tested in accordance with §1323, except that welds that are visually inspected and approved by a qualified welding inspector need not be nondestructively tested if: [ 49 CFR 192.241(b)] 1. the pipe has a nominal diameter of less than 6 inches (152 millimeters); or [ 49 CFR 192.241(b)(1)]2. the pipeline is to be operated at a pressure that produces a hoop stress of less than 40 percent of SMYS and the welds are so limited in number that nondestructive testing is impractical. [ 49 CFR 192.241(b)(2)]C. The acceptability of a weld that is nondestructively tested or visually inspected is determined according to the standards in section 9 of API Std 1104 (incorporated by reference, see §507). Appendix A of API Std 1104 may not be used to accept cracks. [ 49 CFR 192.241(c) ]La. Admin. Code tit. 43, § XIII-1321
Promulgated by the Department of Natural Resources, Office of Conservation, LR 9:230 (April 1983), amended LR 10:522 (July 1984), LR 24:1309 (July 1998), LR 27:1541 (September 2001), LR 30:1242 (June 2004), LR 31:683 (March 2005), LR 33:479 (March 2007), Amended LR 441039 (6/1/2018).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.