Current through Register Vol. 50, No. 11, November 20, 2024
Section III-199 - Technical Proposal-FinalityA. Once the design-builder has been chosen and a contract for a stipulated schedule and sum certain price executed, the price of the design-build contract shall not be increased other than for inflation as prescribed in the contract and for site or other conditions of which the design-builder had no knowledge and should not have had knowledge as a reasonable possibility existing at the site or concerning the design and construction or for changes on the scope of work by the public agency.La. Admin. Code tit. 34, § III-199
Promulgated by the Office of the Governor, Division of Administration, Office of Facility Planning and Control, LR 34:2125 (October 2008).AUTHORITY NOTE: Promulgated in accordance with R.S. 39:121 and RS 38:2225.2.1.