La. Admin. Code tit. 34 § III-111

Current through Register Vol. 50, No. 11, November 20, 2024
Section III-111 - Payments to the Designer
A. Payments on account of designer's services shall be made as follows.
1. Basic Services a. Upon satisfactory completion of all basic services for each phase, submission of all documents to the owner and upon the owner's and user's approval of same, which approval shall not be arbitrarily withheld, payment for the following phases of the designer's services will be made in one lump sum (with the exception of the construction documents phase as described below in Paragraph 2); such payments shall be up to the following percentages of the designer's fixed fee, either interim or final, as apphcable, which percentages are cumulative.

Program completion phase

5 percent

Schematic design phase

15 percent

Design development phase

35 percent

Construction documents phase

60 percent

Bidding and contract phase

65 percent

b. Monthly in proportion to the contractor's certificate for payment for the following phase: Construction phase-95 percent.
c. Upon satisfactory completion and furnishing required documents to the owner for the following phase: Construction close-out phase-100 percent.
i. One percent of the designer's fee up to $2,000 maximum may be withheld from constmction close-out payment until completion of the one-year warranty inspection period.
2. A partial payment for the construction documents phase shall be made when the designer has completed 100 percent of the construction documents and has submitted these to the owner, the user agency, and the other required statutory agencies and the owner determines by inventory check and conformity that all required documents have been submitted, and are sufficiently complete, coordinated and ready to bid, then the designer shall be entitled to a payment of 80 percent of the fee for the construction documents phase. Should the owner's approval of the construction documents not be issued within 45 days of submittal due to no fault of the designer, then the designer shall be paid an additional payment of 10 percent of the fee for the construction documents phase. The balance of the fee for this phase will be due upon the completion of review by owner and user, when corrections have been made, and a complete set of bid documents are submitted to the owner. For projects with an AFC over $10 million, interim payments up to 50 percent of the fee for the construction document phase may be made by agreement between the owner and the designer.
3. If any phase or phase payment is delayed through no fault of the designer, the owner and designer may negotiate a partial payment.
4. The designer shall promptly pay consultants. By signing the professional design services invoice, the designer agrees that all consultants will be promptly paid those amounts due them out of the amount paid to the designer within 45 days. Upon receipt of reasonable evidence of the designer's failure to pay consultants' amounts due them, the owner may withhold all or part of the designer's payment until the owner is satisfied that any amounts owed have been paid or otherwise settled.
B. Payments on account of designer's additional services and for reimbursable expenses shall be made on submission of designer's invoices with supporting data, and their written approval by owner and user agency and issuance of an amendment to the contract covering such services.
C. Payments to the designer on termination, abandonment or suspension shall be made in accordance with §117 and 119, hereinafter.

La. Admin. Code tit. 34, § III-111

Promulgated by the Office of the Governor, Division of Administration, Facility Planning and Control, LR 8:474 (September 1982), amended LR 11:851 (September 1985), LR 13:656 (November 1987), LR 31:1078 (May 2005), Amended by LR 461569 (11/1/2020).
AUTHORITY NOTE: Promulgated in accordance with R.S. 39:1410.