Current through Register Vol. 50, No. 11, November 20, 2024
Section V-30204 - Inspection-General [49 CFR 195.204]A. Inspection must be provided to ensure the installation of pipe or pipeline systems in accordance with the requirements of this Chapter. Any operator personnel used to perform the inspection must be trained and is qualified in the phase of construction to be inspected. An operator must not use operator personnel to perform a required inspection if the operator personnel performed the construction task requiring inspection. Nothing in this section prohibits the operator from inspecting construction tasks with operating personnel who are involved in other construction tasks. [ 49 CFR 195.204 ]B. Each operator shall notify the Pipeline Safety Section of the Louisiana Department of Energy and Natural Resources, by submitting the Notice of Construction form by electronic mail at PipelineInspectors@la.gov of proposed pipeline construction at least seven days prior to commencement of said construction.La. Admin. Code tit. 33, § V-30204
Promulgated by the Department of Natural Resources, Office of Conservation, Pipeline Division, LR 29:2817 (December 2003), repromulgated LR 30:260 (February 2004), Amended LR 441025 (6/1/2018), Amended LR 501244 (9/1/2024).AUTHORITY NOTE: Promulgated in accordance with R.S. 30:753.