La. Admin. Code tit. 13 § I-503

Current through Register Vol. 50, No. 11, November 20, 2024
Section I-503 - Advance Notification; Application
A. An advance notification of intent to apply for tax exemption shall be filed with the department on the prescribed form prior to the beginning of construction or installation of facilities on all projects for tax exemption except as provided in §505.A and B of these rules. An advance notification fee of $250 shall be submitted with the form. The advance notification will expire and become void if no application is filed within 12 months of the estimated project ending date stated in the advance notification. The estimated project ending date as stated on the advance notification may be amended by the applicant if the amendment is made prior to the estimated project ending date.
B. All financial incentive programs for a given project shall be filed at the same time and on the same advance notification. The applicable advance notification fee for each program for which the applicant anticipates applying shall be submitted with the advance notification.
C. An application for tax exemption may be filed with the department on the prescribed form, subject to the following conditions:
1. the filing may be either concurrent with or after filing the advance notification, but no later than 90 days after the beginning of operations or end of construction, whichever occurs first;
2. the deadline for filing the application may be extended pursuant to §523;
3. an applicant filing an application prior to the beginning of operations or end of construction of the project shall file an annual status report with the department on the prescribed form by December 31, until the project completion report and affidavit of final cost are filed. If the applicant fails to timely file a status report the board may, after notice to the applicant, terminate the contract;
4. an application fee shall be submitted with the application in the amount equal to 0.5 percent of the estimated total amount of taxes to be exempted. In no case shall an application fee be smaller than $500 and in no case shall a fee exceed $15,000 per project;
5. The department reserves the right to return the advance notification, application, or affidavit of final cost to the applicant if the form is incomplete or incorrect, or the correct fee is not submitted. The document may be resubmitted with the correct information and fee.
6. If the application is submitted after the filing deadline, the term of exemption available under an initial contract and renewal thereof shall be reduced by one year for each year or portion thereof that the application is late, up to a maximum reduction up to the maximum remaining term. The board may impose any other penalty for late filing that it deems appropriate.
D. The department will provide a copy of the application and all relative information to the Louisiana Department of Revenue (LDR) for review. LDR may require additional information from the applicant. The department must receive a letter-of-no-objection or a letter-of-approval from the LDR, prior to submitting the application to the board for action.
E. In order to receive the boards approval, applications with advance notifications filed after June 24, 2016, shall include an exhibit A containing the following terms and conditions:
1. either the number of jobs and payroll to be created at the project site or the number of jobs and payroll to be retained at the project site where applicable;
2. that the initial exemption contract shall be for a term of no more than five years and may provide for an ad valorem exemption of 80 percent, except that the initial exemption contract for mega projects shall be for a term of no more than five years and may provide for an ad valorem exemption of up to 93 percent;
3. that the applicant can apply for a renewal exemption contract, the consideration of which will be based upon the applicant's performance during the initial term of the contract and that the renewal exemption contract shall be for a term of no more than five years and may provide for an ad valorem exemption of 80 percent, except that the renewal exemption contract for mega projects shall be for a term of no more than five years and may provide for an ad valorem exemption of up to 93 percent;
4. that the department, on behalf of the board, will notify the local governmental entities and the assessor when jobs and/or payroll requirements are not met in accordance with the exhibit A;
5. a provision addressing the penalty for failure to create the requisite number of jobs and/or payroll at the manufacturing establishment, including but not limited to, payment of stipulated sums to the taxing authorities, a reduction in term, reduction in percentage of exemption, or termination of the exemption; and
6. a statement of return on investment (ROI) as determined by the secretary.
F.
1. Applications which provide for a new manufacturing establishment or which provide for an addition to a manufacturing establishment with the creation of new jobs or a compelling reason for the retention of existing jobs shall be favored by the board.
2. In determining whether a company has presented a compelling reason for the retention of existing jobs, the following non-exclusive situations may be considered:
a. to prevent relocation to another state or country;
b. to provide an advantage for investment from a company with multi-state operations with an established competitive capital project program;
c. to employ best practice or innovative, state of the art technology for the establishments industry which shall be deemed to extend the life of the manufacturing establishment;
d. to increase maximum capacity or efficiency;
e. to provide the state a competitive advantage as determined by the secretary or by the board; or
f. upon the sharing of financial information as to the profit/loss of the facility accompanied by evidence that the exemption will prolong the life of, and employment at, the manufacturing establishment.
G. Eligibility of the applicant and the property for the exemption, including whether the activities at the site meet the definition of manufacturing, will be reviewed by the board based upon the facts and circumstances existing at the time the application is considered by the board. The property exempted may be increased or decreased based upon review of the application, project completion report or affidavit of final cost. An application filed prior to completion of construction may be considered by the board and a contract may be executed based upon the best available estimates, subject to adjustments, as necessary, upon review and approval of the project completion report and affidavit of final cost. If the applicant fails to timely file the project completion report or affidavit of final cost the board may, after notice to the applicant, terminate the contract.
H. Upon the boards approval of an application, the department, on behalf of the board, shall, within three business days, transmit a copy of the approval and Exhibit A by mail or electronic mail to each local governmental authority and the assessor and the department shall post notice of the boards approval of an application on the departments website within three business days of approval, upon which date shall begin a notice period of 30 days for the parish governing authority (speaking on behalf of the parish and all parish bodies who are located outside the boundary of any affected municipality who receive a millage), the school board, any applicable municipality (speaking on behalf of the municipality and all municipal bodies who receive a millage) and the sheriff to initiate action to approve or reject the boards action as provided hereinafter.
1. Within the 30-day notice period, the parish governing authority, the school board, or any affected municipality may identify the application on the agenda of a public meeting notice and the sheriff may issue a letter approving or denying the application, and notice of these actions shall be given to the department within 3 business days. A local governmental entity that places the application on the agenda for a public meeting will have an additional 30 days (for a total of 60 days from the start of the notice period) to conduct a public meeting issuing a resolution approving or rejecting the board approved application, and notice of the issuance shall be given to the department within 3 business days. If a local governmental entity does not take action or provide notice as required herein, then the application will be deemed approved by each such entity.
2. Within 60 days of the promulgation of these rules, the local governmental entities for each parish (in consultation with the parish assessor and, upon request, with guidance from the department), shall make best efforts to develop reasonable guidelines for application approval and/or denial and if so desired, penalty guidelines for failure to achieve and maintain jobs and/or payroll as required by the exhibit A.

La. Admin. Code tit. 13, § I-503

Adopted by the State Board of Commerce and Industry, December 9, 1946, amended and promulgated by Department of Commerce, Office of Commerce and Industry, LR 11:97 (February 1985), LR 12:662 (October 1986), amended by the Department of Economic Development, Office of Commerce and Industry, LR 20:864 (August 1994), amended by the Department of Economic Development, Office of Business Development, LR 37:2376 (August 2011), Amended by the Department of Economic Development, Office of Business Development, LR 37:2376 (August 2011), LR 412318 (11/1/2015), Amended by the Department of Economic Development, Office of Business Development, LR 431133 (6/1/2017), Amended LR 441419 (8/1/2018).
AUTHORITY NOTE: Promulgated in accordance with Article VII, Part 2, Section 21(F) of the Louisiana Constitution of 1974.