Kan. Admin. Regs. § 82-17-4

Current through Register Vol. 43, No. 49, December 5, 2024
Section 82-17-4 - Reporting requirements
(a) Each utility shall annually submit to the commission, by March 1, a report in a format approved by the commission listing all net metered facilities connected with the utility during the prior calendar year, pursuant to the act.
(b) Each report shall specify the following information:
(1) Information by customer type, including the following for each net metered facility:
(A) The type of generation resource in operation;
(B) zip code of the net metered facility;
(C) first year of interconnection;
(D) any excess kilowatt-hours that expired at the end of the prior calendar year;
(E) generator size; and
(F) number and type of meters; and
(2) the utility's system retail peak in Kansas and total rated net metered generating capacity for all net metered facilities connected with the utility's system in Kansas.

Kan. Admin. Regs. § 82-17-4

Authorized by K.S.A. 2009 Supp. 66-1269; implementing K.S.A. 2009 Supp. 66-1265, 66-1266, 66-1269, and 66-1271; effective Aug. 6, 2010.