The federal regulations titled "transportation of natural and other gas by pipeline: minimum federal safety standards," 49 C.F.R. Part 192, including appendices B, C, D, and E, as in effect on October 1, 2018, are hereby adopted by reference with the following changes:
Maximum Intervals Between Patrols
Location of Line | Mains in places or on structures where anticipated physical movement or external loading could cause failure or leakage | Mains at all other locations |
Inside Business Districts | 4 1/2 months, but at least four times each calendar year | 7 1/2 months, but at least twice each calendar year |
Outside Business Districts | 7 1/2 months, but at least twice each calendar year | 18 months, but at least once each calendar year |
"Distribution systems: leak surveys and procedures.
Diameter | Percent Graphitization |
2.0 inch | 25% |
3.0 inch and 4.0 inch | 60% |
6.0 inch and 8.0 inch | 75% |
10.0 inch or greater | 90% |
Kan. Admin. Regs. § 82-11-4