Current through Register Vol. 43, No. 49, December 5, 2024
Section 5-8-4 - Construction of diversion works(a) A reasonable period of time for construction of diversion works shall be not less than one full year following the approval of the application to appropriate water. If a person demonstrates that a reasonable long-term schedule for development of diversion works or other infrastructure is in the public interest, that information shall be taken into consideration by the chief engineer in determining a reasonable period of time for the construction of diversion works. (b) For good cause shown by the applicant, a reasonable extension of time to construct the diversion works shall be allowed by the chief engineer, if the request for extension is filed pursuant to the requirements of K.A.R. 5-3-7 and is accompanied by the statutorily required filing fee. (c) If the total time allowed to construct the diversion works has been more than 16 months and fewer than 24 months, an extension of time shall be granted by the chief engineer only if the applicant meets the following criteria: (1) Demonstrates good cause; (2) provides a copy of a contract with the well driller or other information substantiating the intent to proceed to complete the construction of the diversion works in an expeditious manner; (3) files the request for extension pursuant to the requirements of K.A.R. 5-3-7; and (4) submits the statutorily required filing fee. (d) If the total time allowed to construct the diversion works equals or exceeds 24 months, an extension of time may be granted only if the applicant demonstrates to the chief engineer that circumstances beyond the control of the applicant necessitate the extension of time. (e)(1) The applicant shall file a notice of completion of diversion works and the statutorily required field inspection fee with the chief engineer no later than March 1 following the deadline to construct the diversion works. The notice of completion of diversion works shall be filed on a form prescribed by the chief engineer. (2) If a water flowmeter has been required by the chief engineer as a condition of the permit, the applicant shall also file a notice of completion of installation of a water flowmeter on a form prescribed by the chief engineer. This form shall be due at the same time that the notice of completion of diversion works form is due. (f)(1) The applicant shall be sent a notice by the chief engineer giving the applicant 30 days to show that the diversion works were completed within the time allowed in accordance with the terms, conditions, and limitations of the approval of application and to pay the field inspection fee, if it has not already been paid, under either of the following conditions: (A) A notice of completion of diversion works has not been completely and timely filed with the chief engineer. (B) Information on file in the office of the chief engineer indicates that the diversion works were not properly constructed within the time allowed to construct the diversion works, including any authorized extensions of time. (2) The permit shall be dismissed and its priority forfeited if the applicant fails to perform the following: (A) To demonstrate that the diversion works were completed within the time allowed by the approval of application; and (B) to pay the statutorily required field inspection fee, if it has not already been paid. Kan. Admin. Regs. § 5-8-4
Authorized by K.S.A. 82a-706a; implementing K.S.A. 82a-712, K.S.A. 82a-713, and K.S.A. 1999 Supp. 82a-714; effective Sept. 22, 2000.