Kan. Admin. Regs. § 5-40-23
Hazard Size Purpose Minimum
class detention
storm
A 1, 2 Flood control 4% chance
A 3 Flood control 4% chance
A 4 Flood control 2% chance
B All Flood control 2% chance
C All Flood control 2% chance
A 1, 2 All uses other than flood control 50% chance
A 3 All uses other than flood control 50% chance
A 4 All uses other than flood control 20% chance
B All All uses other than flood control 20% chance
C All All uses other than flood control 20% chance
Each dam that has flood control as a purpose shall meet the detention storm requirements for a flood control structure. A dam that is not constructed for flood control purposes and whose auxiliary spillway meets the requirements for a service spillway in K.A.R. 5-40-57 shall not be required to meet any minimum detention storm requirement in the table in this subsection.
Kan. Admin. Regs. § 5-40-23