Current through Register Vol. 47, No. 8, October 30, 2024
Rule 567-65.208 - Construction certification(1) The owner of an open feedlot operation who is issued a construction permit for a settled open feedlot effluent basin or AT system as provided in rule 567-65.203 (455B,459A) shall submit to the department a construction certification from a PE certifying all of the following:a. The settled open feedlot effluent basin or AT system was constructed in accordance with the design plans submitted to the department as part of an application for a construction permit pursuant to rule 567-65.204 (455B,459A). If the actual construction deviates from the approved design plans, the construction certification shall identify all changes and certify that the changes were consistent with all applicable standards of these rules.b. The settled open feedlot effluent basin or AT system was inspected by the PE after completion of construction and before commencement of operation.(2) A written record of an investigation for drainage tile lines, including the findings of the investigation and actions taken to comply with subrules 65.206(1) and 65.207(3), shall be submitted as part of the construction certification.Iowa Admin. Code r. 567-65.208
Adopted by IAB November 9, 2016/Volume XXXIX, Number 10, effective 12/14/2016Adopted by IAB May 15, 2024/Volume XLVI, Number 24, effective 6/19/2024