Rule 567-40.4 - Public water supply construction permit application procedures(1)General procedures. Applications for written approval from the department for any new construction or for reconstruction pursuant to 567-Chapter 43 shall consist of complete plans and specifications, application fee, and appropriate water supply construction permit application schedules. Upon review, the department will issue a construction permit for approval of a project if the review shows that the project meets all departmental design standards in accordance with 567-Chapter 43. Approval of a project which does not meet all department design standards will be denied unless a variance as provided by 567-paragraph 43.3(2)"b " is granted. A variance may be requested at the time plans and specifications are submitted or after the design discrepancy is pointed out to the applicant. The department may review submitted project plans and specifications and provide comments and recommendations to the applicant. Departmental comments and recommendations are advisory, except when departmental review determines that a facility does not comply with the plans or specifications as approved by the department or comply with the design standards pursuant to the criteria for certification of project design. The owner of the system must correct the deficiency in a timely manner as set forth by the department.
(2)Public water sources and below-ground level water storage facilities -site survey. For public water sources and for below-ground level finished water storage facilities, a site survey and approval must be made by the department. The manner and procedures for applying for and processing a site survey are the same as in 40.4(1) except that the following information must be submitted by the applicant's engineer. a. A preliminary engineering report or a cover letter which contains a brief description of the proposed source or storage facility and assurance that the project is in conformance with the long-range planning of the area.b. Completed Schedule la - General Informationc. Completed Schedule 4 - Water Supply Facility Site Selectiond. A detailed map showing all potential sources of contamination (see 567-Chapter 43, Table A) within:(1) 1,000 feet of a proposed well location. The scale shall not be smaller than 1 inch = 200 feet.(2) 200 feet of a proposed below-ground level finished water storage facility.(3) 2,500 feet from a proposed surface water source and a plat showing all facilities more than 2,5 00 feet from an impoundment (within the drainage area) that may be potential sources of contamination. The scale shall not be smaller than 1 inch = 660 feet.(4) Six miles upstream of a proposed river intake.(3)Modifications of an approved water supply construction project. Persons seeking to make modifications to a water supply construction project after receiving a prior construction permit from the department shall submit an addendum to plans and specifications, a change order or revised plans and specifications at least 30 days prior to planned construction, and the appropriate fee. The department shall review the submitted material within 30 days of submission and shall issue a supplemental permit if the proposed modifications meet departmental standards.(4)Certification of project design. A permit shall be issued for the construction, installation or modification of a public water supply system or part of a system or for a water supply distribution system extension if a qualified, licensed professional engineer certifies that the plans and specifications comply with federal and state laws and regulations or that a variance to standards has been granted by the department. Refer to Schedule 1a.Iowa Admin. Code r. 567-40.4