Current through Register Vol. 47, No. 11, December 11, 2024
Rule 199-24.11 - Site preparation(1) In the event no certificate has been issued after 90 days from the commencement of the hearing, the commission may permit the applicant to begin work to prepare the site for construction of the facility. Any activities conducted pursuant to this rule shall have no probative value to the commission's decision concerning the actual issuance of a certificate.(2) In the event the commission denies an application for a certificate or an amendment to a certificate, applicants who have received permission to begin site preparation, pursuant to 24.11(1), shall restore the site, in accordance with the commission order denying the application.Iowa Admin. Code r. 199-24.11
Amended by IAB April 11, 2018/Volume XL, Number 21, effective 5/16/2018Editorial change: IAC Supplement 7/24/2024