860 Ind. Admin. Code 1-5-8

Current through October 31, 2024
Section 860 IAC 1-5-8 - Completion of plumbing work

Authority: IC 25-28.5-1-7

Affected: IC 25-28.5-1-27.1

Sec. 8.

Plumbing contractors shall complete all plumbing work which they have contracted to perform unless they have legal cause to not perform the work.

860 IAC 1-5-8

Indiana Plumbing Commission; 860 IAC 1-5-8; filed Nov 21, 1989, 1:15 p.m.: 13 IR 631; readopted filed May 29, 2001, 10:00 a.m.: 24 IR 3237; readopted filed Jul 19, 2007, 12:57 p.m.: 20070808-IR-860070061RFA; readopted filed November 25, 2013, 9:21 a.m.: 20131225-IR-860130282RFA
Readopted filed 11/26/2019, 3:46 p.m.: 20191225-IR-860190189RFA
Readopted filed 1/17/2024, 5:34 p.m.: 20240214-IR-860230763RFA