675 Ind. Admin. Code 21-1-1

Current through December 4, 2024
Section 675 IAC 21-1-1 - Installation and alteration permit; registration; application; expiration

Authority: IC 22-13-2-13; IC 22-15-5-2

Affected: IC 22-13; IC 22-14; IC 22-15-5-3

Sec. 1.

(a) An installation permit is required prior to commencement of work for an installation of a new regulated lifting device. An alteration permit is required prior to commencement of work for an alteration to an existing regulated lifting device.
(b) An application for an installation or alteration permit shall be made to the office of the state building commissioner on forms provided by the office. Each application shall contain the following:
(1) The name, address, e-mail address, and fax number of the elevator contractor that will be installing or altering the regulated lifting device, and if applicable, the license number of the elevator contractor.
(2) The name, address, and e-mail address of the owner of the building in which the new regulated lifting device is being installed or the existing regulated lifting device is being altered.
(3) The name, address, and e-mail address of the user of the regulated lifting device.
(4) All information required under IC 22-15-5-3(c) for registration of the regulated lifting device. This includes the following for the regulated lifting device:
(A) The type.
(B) The rated load and speed.
(C) The name of the manufacturer.
(D) The location.
(E) The nature of use.
(5) Complete plans, including:
(A) copies of specifications and accurately scaled and fully dimensioned plans showing the location of the installation in relation to the plans and elevation of the building;
(B) plans showing the location of the machine room and the equipment to be installed, relocated, or altered;
(C) plans showing the structural supporting members, including foundations; and
(D) a specification of all materials employed and loads to be supported or conveyed.

These plans must be sufficient to show that the installation or alteration will comply with all applicable equipment laws and must be sufficiently complete to illustrate all details of construction and design.

(6) The required fee.
(7) The affirmations by the appropriate signatories as required under section 1.5 of this rule.

675 IAC 21-1-1

Fire Prevention and Building Safety Commission; 675 IAC 21-1-1; filed Aug 30, 1985, 11:52 a.m.: 9 IR 38, eff Oct 1, 1985; filed Sep 27, 1989, 4:30 p.m.: 13 IR 285; readopted filed Sep 11, 2001, 2:49 p.m.: 25 IR 530; filed Dec 3, 2002, 3:05 p.m.: 26 IR 1083; readopted filed Aug 20, 2009, 12:42 p.m.: 20090916-IR-675090380RFA; readopted filed Aug 8, 2012, 8:08 a.m.: 20120905-IR-675120260RFA
Readopted filed 7/3/2018, 2:22 p.m.: 20180801-IR-675180204RFA