355 Ind. Admin. Code 10-7-7

Current through September 4, 2024
Section 355 IAC 10-7-7 - Construction

Authority: IC 15-16-2-1.5

Affected: IC 15-16-2

Sec. 7.

(a) The owner or operator shall notify the state chemist in writing at least two (2) days prior to scheduled construction of a storage structure. Multiple notices, with identification of the parts of the storage structure that are completed at the time of submittal, are required if an owner or operator performs partial construction of an approved structure and plans to utilize that portion prior to completing construction of the entire storage structure.
(b) Any field tiles or drainage outlets encountered during construction must be blocked or rerouted in accordance with any applicable local approval requirements and be cut back at least fifty (50) feet from the edge of any:
(1) berm;
(2) concrete pit; or
(3) earthen storage structure.
(c) The applicant shall execute and send to the state chemist a notarized affidavit, under penalty of perjury, that a storage structure was constructed, and shall be operated, in accordance with the requirements of this article, as follows:
(1) The affidavit shall be submitted:
(A) on a form provided by the state chemist;
(B) within thirty (30) days after the date construction is completed; and
(C) prior to the introduction of any processed manure.
(2) The affidavit shall include identification of the parts of the storage structure that are completed at the time of submittal.
(3) If an owner or operator performs partial construction of an approved storage structure and plans to utilize that portion prior to completing construction of the entire storage structure, multiple affidavits shall be submitted.
(d) The certification required by section 5(e) of this rule must be completed prior to the introduction of processed manure.

355 IAC 10-7-7

State Chemist of the State of Indiana; 355 IAC 10-7-7; filed 3/17/2022, 12:13 p.m.: 20220413-IR-355210455FRA