329 Ind. Admin. Code 11-12-2

Current through December 4, 2024
Section 329 IAC 11-12-2 - Preoperational requirements

Authority: IC 13-14-8-7; IC 13-15-2-1; IC 13-19-3-1

Affected: IC 13-30-2; IC 36-9-30

Sec. 2.

Before beginning operation, a solid waste processing facility must complete the initial facility development outlined in the permitted plans and specifications. Initial facility development includes the following:

(1) Construction of buildings or structures and on-site roads.
(2) Installation of equipment for storage, processing, and handling of solid waste.
(3) Installation of the following:
(A) Access control.
(B) Sanitary facilities.
(C) Signs.
(D) Communication devices.
(E) Utilities.
(4) Financial assurance must be established under 329 IAC 11-16 for the solid waste processing facility.

329 IAC 11-12-2

Solid Waste Management Board; 329 IAC 11-12-2; filed Mar 14, 1996, 5:00 p.m.: 19 IR 1941; readopted filed Jan 10, 2001, 3:25 p.m.: 24 IR 1535; readopted filed May 14, 2007, 1:53 p.m.: 20070523-IR-329070138BFA; filed Jun 28, 2010, 2:11 p.m.: 20100728-IR-329060070FRA
Readopted filed Jun 6, 2016, 11:52 a.m.: 20160706-IR-329160144BFA