Current through December 25, 2024
Section 329 IAC 10-17-10 - Geosynthetic clay component of the liner; design, construction, and CQA/CQC requirementsAuthority: IC 13-14-8-7; IC 13-15-2-1; IC 13-19-3-1
Affected: IC 13-30-2; IC 36-9-30
Sec. 10.
(a) The geosynthetic clay liner (GCL) must meet current industry design standards and any additional design standards necessary to obtain an adequate GCL, as specified in the construction plans or as determined by the commissioner.(b) The project engineer shall ensure that adequate quality control and quality assurance procedures have been followed throughout all of the following operations: (1) Refining of raw materials, based on the manufacturer's documentation, and manufacturing of geosynthetic clay liner.(2) Storage, handling, and shipment of the geosynthetic clay liner.(3) Installation of the geosynthetic clay liner, including:(A) proper placement, joining, and repair procedures; and(B) proper backfilling or covering procedures.Solid Waste Management Board; 329 IAC 10-17-10; filed Mar 14, 1996, 5:00 p.m.: 19 IR 1837