326 Ind. Admin. Code 2-7-18

Current through October 23, 2024
Section 326 IAC 2-7-18 - Permit review by the U.S. EPA

Authority: IC 13-14-8; IC 13-15; IC 13-17

Affected: IC 13-11

Sec. 18.

(a) Except as otherwise waived by the U.S. EPA, the commissioner shall provide to the U.S. EPA a copy of each Part 70 permit application (including any application for permit modification), each draft and proposed permit, and each final permit in accordance with this section.
(b) The commissioner shall submit the draft permit to the U.S. EPA no later than the beginning of the thirty (30) day public review period. The thirty (30) day public review period and the forty-five (45) day U.S. EPA review period may run concurrently in the following manner:
(1) If the commissioner receives no comments from the public or any affected state, or receives comments that are not based on applicable requirements or the requirements of this rule, the commissioner will so notify the U.S. EPA and transmit a copy of the draft permit, signed by the commissioner, which shall be the proposed permit. The U.S. EPA's review period will end forty-five (45) days from the date it initially received the draft permit.
(2) If the commissioner receives comment from the public or an affected state that is based on an applicable requirement or a requirement of this rule, but determines not to revise the permit, the commissioner shall notify the U.S. EPA and any affected state making such comment in writing of the determination not to revise the permit and the reasons therefore at or after the close of the thirty (30) day public comment period. The commissioner shall include a copy of the draft permit, signed by the commissioner, which shall be the proposed permit. U.S. EPA's review period will end forty-five (45) days from the date it initially received the draft permit unless the U.S. EPA notifies the commissioner within fifteen (15) days of its receipt of the proposed permit that the full forty-five (45) day review period is required.
(3) If the commissioner makes revisions to the draft permit in response to comments from the public or an affected state, the commissioner shall submit a signed copy of the revised permit, which shall be the proposed permit, to the U.S. EPA. The U.S. EPA shall complete its review within forty-five (45) days of receipt of the revised proposed permit and all necessary supporting documentation.
(c) No permit for which an application must be transmitted to the U.S. EPA under subsection (a) shall be issued by the commissioner if the U.S. EPA, in accordance with 40 CFR 70.8(c)(2) *, objects in writing to its issuance within forty-five (45) days after receipt of the draft or proposed permit and all necessary supporting information as described in subsection (b).
(d) If the U.S. EPA does not object to the issuance of a Part 70 permit under subsection (c), any person may petition the U.S. EPA, within sixty (60) days after the expiration of the U.S. EPA's forty-five (45) day review period, to make such objection. Any such petition shall be based only on objections to a Part 70 permit that were raised with reasonable specificity during the public comment period provided under section 17 of this rule, unless the petitioner demonstrates that it was impracticable to raise such objections within such period or unless the grounds for such objection arose after such period. Such a petition for review does not stay the effectiveness of a permit or its requirements if the permit was issued after the end of the U.S. EPA's forty-five (45) review period and prior to a U.S. EPA objection. If the U.S. EPA objects to a Part 70 permit prior to issuance as a result of a petition filed under this subsection, the commissioner shall not issue the permit until the U.S. EPA's objection has been resolved, except that a petition for review does not stay the effectiveness of a permit or its requirements if the permit was issued after the end of the forty-five (45) day review period and prior to the U.S. EPA's objection. If the commissioner has issued a permit prior to receipt of a U.S. EPA objection under this subsection, the U.S. EPA will modify, terminate, or revoke the permit, consistent with the procedures in section 9(d) of this rule, except in unusual circumstances, and the commissioner may thereafter issue only a revised permit that satisfies the U.S. EPA's objection. In any case, the source will not be in violation of the requirement to have submitted a timely and complete application.

*This document is incorporated by reference. Copies may be obtained from the Government Printing Office, 732 North Capitol Street NW, Washington, D.C. 20401 or are available for review and copying at the Indiana Department of Environmental Management, Office of Air Quality, Indiana Government Center-North, Tenth Floor, 100 North Senate Avenue, Indianapolis, Indiana 46204.

326 IAC 2-7-18

Air Pollution Control Board; 326 IAC 2-7-18; filed May 25, 1994, 11:00 a.m.: 17 IR 2267; errata filed Dec 12, 2002, 3:35 p.m.: 26 IR 1566; filed Aug 26, 2004, 11:30 a.m.: 28 IR 21