312 Ind. Admin. Code 29-33-7

Current through December 4, 2024
Section 312 IAC 29-33-7 - Notification to underground gas storage operator

Authority: IC 14-10-2-4; IC 14-37-3

Affected: IC 14-37

Sec. 7.

At least ten (10) days before commencing the plugging of any well located within one-half (1/2) mile of an underground gas storage facility boundary, the owner or operator shall give written notice of intent to plug the well to the underground gas storage facility operator of the well. The notice shall:

(1) include a copy of the well plugging plan;
(2) indicate the date on which plugging is planned to commence; and
(3) provide the opportunity for the underground storage operator to have a representative present to witness the well plugging operations.

312 IAC 29-33-7

Natural Resources Commission; 312 IAC 29-33-7; filed 12/1/2017, 10:35 a.m.: 20171227-IR-312160230FRA
Readopted filed 1/17/2023, 1:53 p.m.: 20230215-IR-312220328RFA