Current through December 4, 2024
Section 312 IAC 29-33-1 - Requirement to plug and abandon wellsAuthority: IC 14-10-2-4; IC 14-37-3
Affected: IC 14-37
Sec. 1.
An owner or operator must plug and abandon a well that:
(1) is determined to be a dry hole;(2) ceases to produce oil, natural gas, or coal bed methane; or(3) is no longer operated for the purpose for which the well is permitted; unless the owner or operator is authorized to delay the plugging and abandonment of the well under section 3 of this rule or is granted approval to temporarily abandon the well under section 4 of this rule.
Natural Resources Commission; 312 IAC 29-33-1; filed 12/1/2017, 10:35 a.m.: 20171227-IR-312160230FRAReadopted filed 1/17/2023, 1:53 p.m.: 20230215-IR-312220328RFA