Current through December 4, 2024
Section 312 IAC 25-4-7 - Permit applications; format and contents reviewAuthority: IC 14-34-2-1
Affected: IC 14-34
Sec. 7.
Each application for a surface coal mining and reclamation permit under a regulatory program shall be reviewed as to its completeness prior to formal review and shall include the following:
(1) This completeness review shall be completed not later than fifteen (15) working days after such permit is submitted.(2) The director shall contact the applicant not later than five (5) working days after a permit is reviewed for completeness and shall state: (A) which portions of the permit application are incomplete; and(B) those conditions and information requirements necessary to complete the application.Natural Resources Commission; 312 IAC 25-4-7; filed Jun 21, 2001, 2:53 p.m.: 24 IR 3440, eff Dec 1, 2001; readopted filed May 29, 2007, 9:51 a.m.: 20070613-IR-312070146RFA; readopted filed Sep 19, 2013, 10:12 a.m.: 20131016-IR-312130125RFAReadopted filed 3/26/2019, 3:40 p.m.: 20190424-IR-312190011RFA