Current through December 4, 2024
Section 312 IAC 25-4-5 - Permit applications; filing and deadlinesAuthority: IC 14-34-2-1
Affected: IC 14-34
Sec. 5.
(a) Each person who conducts or expects to conduct new surface coal mining and reclamation operations shall file an application for a permit for those operations no later than one hundred eighty (180) days prior to the proposed commencement of such operations.(b) An application for renewal of a permit shall be filed with the director at least one hundred twenty (120) days before the expiration of the permit involved.(c) Any application for revision of a permit shall be filed with the director at least one hundred twenty (120) days before the date on which the permittee expects to revise surface coal mining or reclamation operations.(d) Any application for a new permit required for a person succeeding by transfer, sale, or assignment of rights granted under a prior permit shall be filed with the director not later than thirty (30) days after that succession is approved by the director.Natural Resources Commission; 312 IAC 25-4-5; filed Jun 21, 2001, 2:53 p.m.: 24 IR 3439, eff Dec 1, 2001; readopted filed May 29, 2007, 9:51 a.m.: 20070613-IR-312070146RFA; readopted filed Sep 19, 2013, 10:12 a.m.: 20131016-IR-312130125RFAReadopted filed 3/26/2019, 3:40 p.m.: 20190424-IR-312190011RFA