25 Ind. Admin. Code 2-6-8

Current through December 4, 2024
Section 25 IAC 2-6-8 - Low bid exceeds available funds

Authority: IC 4-13-2-9; IC 4-13.6-3-1

Affected: IC 4-13.6

Sec. 8.

If the low bid exceeds the allocation, and additional funds are requested but not approved, then bids shall be rejected and project suspended or rebid with design revised in value equivalent to the overrun.

25 IAC 2-6-8

Indiana Department of Administration; Public Works Division Sec F,8; filed Feb 29, 1972, 4:10 pm: Rules and Regs. 1973, p. 6; readopted filed Nov 20, 2001, 9:30 a.m.: 25 IR 1265; readopted filed Aug 26, 2008, 8:31 a.m.: 20080910-IR-025080549RFA; readopted filed Oct 18, 2013, 1:38 p.m.: 20131113-IR-025130403RFA
Readopted filed 11/4/2019, 3:40 p.m.: 20191204-IR-025190494RFA
Readopted filed 10/25/2024, 12:07 p.m.: 20241120-IR-025240218RFA