Authority: IC 4-13-2-9; IC 4-13.6-3-1
Affected: IC 4-13.6; IC 5-16-1-2
Sec. 3.
The executive secretary of the certification board or his or her designee shall, immediately before the designated time for acceptance of bids for projects estimated at one hundred fifty thousand dollars ($150,000) or more, review the prequalification of all bidders submitting bids. If:
(1) a bid packet is received; and(2) the bidder is not currently prequalified with the certification board; the bid shall be rejected.
Indiana Department of Administration; Public Works Division Sec F,3; filed Feb 29, 1972, 4:10 p.m.: Rules and Regs. 1973, p.5; filed Feb 3, 1982, 1:05 p.m.: 5 IR 512; readopted filed Nov 20, 2001, 9:30 a.m.: 25 IR 1265; filed Nov 14, 2007, 11:10 a.m.: 20071212-IR-025060515FRA; readopted filed Oct 18, 2013, 1:38 p.m.: 20131113-IR-025130403RFAReadopted filed 11/4/2019, 3:40 p.m.: 20191204-IR-025190494RFA