25 Ind. Admin. Code 2-5-4

Current through December 4, 2024
Section 25 IAC 2-5-4 - Exception from bidding; emergency work

Authority: IC 4-13-2-9; IC 4-13.6-3-1

Affected: IC 4-13.6; IC 5-16-1-1.1; IC 36-1-12

Sec. 4.

The commissioner may authorize contracts to perform necessary work or construction in an emergency as described in 25 IAC 2-11 without calling for bids under normal procedures. Authorization for such emergency work will be given verbally by the commissioner or the director if so delegated. In either case, the award shall be confirmed in writing with copies filed with the department as provided under 25 IAC 2-11.

25 IAC 2-5-4

Indiana Department of Administration; Public Works Division Sec E,4; filed Feb 29, 1972,4:10 p.m.: Rules and Regs. 1973, p.4; filed Feb 3, 1982, 1:05 p.m.: 5 IR 512; readopted filed Nov 20, 2001, 9:30 a.m.: 25 IR 1265; filed Nov 14, 2007, 11:10 a.m.: 20071212-IR-025060515FRA; readopted filed Oct 18, 2013, 1:38 p.m.: 20131113-IR-025130403RFA
Readopted filed 11/4/2019, 3:40 p.m.: 20191204-IR-025190494RFA
Readopted filed 10/25/2024, 12:07 p.m.: 20241120-IR-025240218RFA