25 Ind. Admin. Code 2-14-1

Current through December 4, 2024
Section 25 IAC 2-14-1 - Purposes of the certification board; contractor's prequalification approval

Authority: IC 4-13-2-9; IC 4-13.6-3-1

Affected: IC 4-13.6

Sec. 1.

The purposes of the certification board are to determine the following:

(1) Which applicant contractors have the:
(A) experience;
(B) physical capabilities; and
(C) financial resources;

to bid or to subcontract on state construction projects valued at one hundred fifty thousand dollars ($150,000) or more that are implemented through the facilities of the division and all other agencies so required by statute.

(2) Which applicant designers have the:
(A) professional capabilities;
(B) manpower; and
(C) experience;

necessary to perform architectural, engineering, or related professional work on state projects likewise implemented through the division.

25 IAC 2-14-1

Indiana Department of Administration; Public Works Division Sec N,1; filed Feb 29, 1972, 4:10 p.m.: Rules and Regs. 1973, p.10; filed Feb 3, 1982, 1:05 p.m.: 5 IR 517; readopted filed Nov 20, 2001, 9:30 a.m.: 25 IR 1265; filed Nov 14, 2007, 11:10 a.m.: 20071212-IR-025060515FRA; readopted filed Oct 18, 2013, 1:38 p.m.: 20131113-IR-025130403RFA
Readopted filed 11/4/2019, 3:40 p.m.: 20191204-IR-025190494RFA
Readopted filed 10/25/2024, 12:07 p.m.: 20241120-IR-025240218RFA