Authority: IC 4-13-2-9; IC 4-13.6-3-1
Affected: IC 5-16-5
Sec. 2.
Upon receipt of such final payment request and necessary affidavits, the billing will be passed for payment unless certificates of non-payment as submitted by subcontractors or materialmen have not yet been resolved. In that event, the amounts alleged to be owed shall be deducted from the contractor billings and the balance passed for payment as a partial payment.
25 IAC 2-10-2