Authority: IC 8-1-2-47; IC 8-1-2-69; IC 8-1-2-89
Affected: IC 8-1-1-3; IC 8-1-2-89
Sec. 36.
A deposit shall be held by the utility as a customer's advance for construction. Any deposit which is not subject to refund because of the running of the ten (10) year period as provided in section 35 of this rule, shall be transferred by the utility to contributions in aid of construction. If the original depositor for a main extension forfeits all rights to a refund, except for subsequent connector's fees, as provided in section 32(a)(3) of this rule, the payment must be included in contributions in aid of construction and the associated taxes shall be deducted from contributions in aid of construction. All other deposits must be held as customers' advances for construction until returned to the original depositor or be reported as required under IC 32-9-1-36[Repealed by P.L. 31-1995, SECTION 9, effective July 1, 1996.], and as provided under section 35 of this rule.
170 IAC 8.5-4-36