Ill. Admin. Code tit. 8 § 1000.150

Current through Register Vol. 48, No. 49, December 6, 2024
Section 1000.150 - Modifications and Alterations
a) A permit shall be amended before the commencement of any modification to the facility. This includes any change that modifies the approved permit design capability of production or process areas, including change of capacity, efficiency or processes.
b) Before making any modification to a permitted facility, the cultivation center must complete an Application for Permit and Construction Approval and submit the application with the appropriate schedules to the Department.
c) An amendment to the permit shall not be required for alterations at the facility.

Ill. Admin. Code tit. 8, § 1000.150

Adopted at 38 Ill. Reg. 16731, effective 7/25/2014.