The Well Completion Report shall be completed on a form prescribed by the Department and shall contain:
A Well Completion Report shall be submitted to the Department within 30 days after the conclusion of initial completion activities (i.e., setting of tubing and packer) or within 30 days after the expiration of the permit if the well was not drilled or converted.
A Well Completion Report shall be completed and submitted to the Department for each recompletion of any existing injection well. Recompletion includes injection into a zone not previously used for injection in the well. The Well Completion Report shall be submitted within 30 days after the completion of any such workover or recompletion activity.
A copy of all open hole wire line or geophysical logs run on the well shall be submitted to the State Geological Survey within 90 days after drilling ceases but, in the case of a conversion of an existing well, only if the well is deepened.
The Department shall notify the permittee when cuttings are required to be collected. Drill cuttings shall be collected for each run drilled in cable tool wells and each 10 feet of distance drilled in rotary or air drilled wells. The permittee shall obtain containers for the cuttings, and deliver the cuttings to the Illinois State Geological Survey in Champaign, Illinois. When cuttings are required, a Drilling Time log shall also be submitted.
Drill cuttings shall be submitted for each well when drill cuttings have not previously been submitted from any well within 1/2 mile of the newly permitted well. If the newly permitted well is drilled to a depth greater than any other well within 1/2 mile, drill cuttings shall be requested from the approximate previously submitted depth to the total depth in the newly permitted well.
The permittee of each Class II UIC well shall file an Annual Well Status Report on forms prescribed by the Department. The report shall be filed by May 1 of each year for the preceding calendar year for all wells which have not received Department approval for temporary abandonment or been plugged by the end of the reporting year, and shall include:
The operator of an enhanced oil recovery project shall complete an annual project report on forms prescribed by the Department and submit the report to the State Geological Survey by May 1 of each year.
Ill. Admin. Code tit. 62, § 240.780
Amended at 35 Ill. Reg. 13281, effective July 26, 2011