8.0 Excellent
7.0 Good
6.0 Satisfactory
4.0 Marginal
2.0 Poor
8.0 The contractor exceeded project requirements in all areas considered.
7.0 The contractor exceeded project requirements in a majority of areas considered.
6.0 The contractor met project requirements in all areas considered.
4.0 The contractor did not meet project requirements in one area considered.
2.0 The contractor did not meet project requirements in two or more areas considered.
8.0 The contractor exceeded project requirements in all areas considered and completed the project well ahead of schedule.
7.0 The contractor exceeded project requirements in a majority of areas considered and the project was completed slightly ahead of schedule.
6.0 The contractor met project requirements in all areas considered and the scheduled completion date was met.
4.0 The contractor did not meet project requirements in one area considered and occasionally did not work when conditions permitted. The scheduled completion date was met.
2.0 The contractor did not meet project requirements in two or more areas considered and the scheduled completion date was not met.
8.0 The contractor exceeded project requirements in all areas considered.
7.0 The contractor exceeded project requirements in a majority of areas considered.
6.0 The contractor met project requirements in all areas considered.
4.0 The contractor did not meet project requirements in one area considered.
2.0 The contractor did not meet project requirements in two or more areas considered.
8.0 The contractor exceeded project requirements in all areas considered.
7.0 The contractor exceeded project requirements in a majority of areas considered.
6.0 The contractor met project requirements in all areas considered.
4.0 The contractor did not meet project requirements in one area considered.
2.0 Either the contractor did not meet project requirements in two or more areas considered or the contractor committed an act or omission which seriously compromised the safety of the public.
8.0 The contractor exceeded project requirements.
7.0 The contractor met project requirements through extraordinary effort and initiative.
6.0 The contractor met project requirements with minimum effort and initiative.
4.0 The contractor met project requirements, but had to be motivated by Department personnel.
2.0 The contractor did not meet project requirements.
8.0 The contractor exceeded project requirements.
7.0 The contractor exceeded project in a majority of the areas considered.
6.0 The contractor met project requirements in all areas.
4.0 The contractor did not meet the project requirements in one area considered.
2.0 The contractor did not meet the contract requirements in two or more areas.
8.0 The contractor exceeded QC/QA requirements in all areas considered.
7.0 The contractor exceeded QC/QA requirements in a majority of areas considered.
6.0 The contractor met QC/QA requirements in all areas considered.
4.0 The contractor did not meet QC/QA requirements in one area considered.
2.0 The contractor did not meet QC/QA requirements in two or more areas considered.
Ill. Admin. Code tit. 44, § 650.240
Amended at 30 Ill. Reg. 16373, effective October 10, 2006