For the purposes of determining operational readiness following completion of physical construction, the Agency must l establish permit conditions, including but not limited to allowable waste feeds and operating conditions, in the permit to a new hazardous waste incinerator. These permit conditions will be effective for the minimum time required to bring the incinerator to a point of operational readiness sufficient to conduct a trial burn, not to exceed 720 hours operating time for treatment of hazardous waste. The Agency must extend the duration of this operation period once, for up to 720 additional hours, at the request of the applicant when good cause is shown. The permit must be modified to reflect the extension according to Section 703.280.
Ill. Admin. Code tit. 35, § 703.222
Amended at 27 Ill. Reg. 3496, effective February 14, 2003
BOARD NOTE: Derived from 40 CFR 270.62(a) (2002).